Go To Search
RSSEmailPrint
Click to Home
Project: Trask Street Area
The Trask Street Area Public Improvements Project is scheduled to begin at 7 a.m. on October 15, 2019.  This project will result in improvements to certain water mains & water services; make sewerage system improvements including pipe relining, pipe replacement, and manhole rehabilitation; complete sidewalk & curbing replacement; complete full width street paving; and place pavement markings & upgraded signage. The Contractor has until June 2021 to complete the project, fully, but the job is expected to be completed in a more timely manner.  This project may also lead the other public utilities, National Grid, Verizon, Comcast, etc. to undertake certain maintenance efforts on their infrastructure in the Neighborhood, as well.

The Contractor, N. Granese & Sons, Inc., will generally be working between 7 a.m and 5 p.m, Monday through Friday, excluding legal holidays.  At times work may go later in the day due to unforeseen circumstances, and weekend work will almost never occur unless there is an emergency situation that needs to be addressed. 

The following is an outline schedule for the Trask Street Area Improvements Project. 

Work will start at 7 a.m. on October 15, 2019.  The initial work will involve Granese's efforts to layout by pass water pipe to insure uninterrupted water service for domestic use and fire flow. It is expected that this effort will take approximately two days (Tues 10/15 & Wed 10/16).  Once the temporary "main" is in place, it will be flushed and then tested to meet the Contract's and State's specifications, then the Contractor will connect the temporary main.  It is expected that this will be done Wed 10/16, Thurs 10/17 and Fri 10/18.

On approximately Monday, October 21, 2019, the Contractor will begin the work to replace the water mains beginning at the intersection of Sargent-Millett-Cedar Streets and will proceed up Warner to Trask Street ending at the intersection of Summit Street.


 Additional Information:

For the duration of the project the areas shown on the attached map will be active construction sites so you should be careful walking and drive at a reduced speed accordingly. Construction activities may require the closing of the street to through traffic. On the days when construction is ongoing, it is important not to have any cars parked in the roadway between the hours of 7:00 A.M. and 5:00 P.M. “No Parking” signs will be posted in advance of construction and parking restrictions will remain in effect until construction is complete for that day. You will have access to your driveway and may park on the street after work hours; however, as the project progresses; certain activities may require limited access or parking.

We apologize in advance for any inconvenience you may incur during this process. The City appreciates your patience and forbearance during this important project. We feel that your cooperation will make this project a success. Granese's work will be done under the direct supervision of CDM-Smith, Inc. (CDM-S), the City’s Design Engineers.  The on-site Project Representative/Inspector is Steve DeFeo, who is available during working hours (7 a.m. to 5 p.m.) on his mobile phone at 508-523-9284. If you have an issue, Steve should be your first call, as he will be in the best position to know what is going on with the project and will be able to address your immediate concerns.

The City of Gloucester DPW will be monitoring the project.  Please contact Paul Keane, City Engineer or Ryan Marques, Assistant City Engineer, at 978-325-5600 if you have questions or concerns about the project.

If you need access during construction due to special circumstances, please click here for the Continuation of Special Needs form that will need to be filled out and returned to: Paul G. Keane, P.E., City Engineer, City of Gloucester – DPW Engineering Division City Hall Annex, 2nd Floor, 3 Pond Road, Gloucester, Massachusetts 01930 Phone: 978-325-5335 Email:

Click here to view the Scope of Work.

Click here to view the Area Improvement Project Extent.

20191004_TraskArea (1).png



Home     Contact Us     Documents     Pay Bills     Departments     Translate     Sitemap     Accessibility     Employment     Copyright     Powered by CivicPlus