Start-up and Continuation of Brier Neck Water Main Replacement and Lining Project

Brier Neck web

Start-up and Continuation of Brier Neck Water Main Replacement and Lining Project

Residents Affected: Witham Rd, Salt Island Rd, Barberry Way, Brier Neck, Cliff Rd, Palfrey Rd, Prospect Terrace, Arland Terrace

This notice has been prepared to inform you that the water main construction will soon resume in your neighborhood to improve the service and reliability of the municipal water distribution system. The project will involve water pipe rehabilitation and installation of water mains, fire hydrants, and valves on Cliff Rd., Palfrey Rd., and parts of Salt Island Rd., by the City’s Contractor N. Granese & Sons, Inc. of Salem, MA (781-201-1705).

Sequence and Schedule:

The water work is scheduled to begin the week of March 22, 2021 and is anticipated to take 4 to 6 weeks to complete. Please refer to the full notice about project scope, special needs forms, projected times, no parking notices and related activities.

Contact:

If you have any concerns about the temporary water bypass piping or construction issues, please call N. Granese & Sons 24-hr. number at 781-201-1705. If you have any questions, or require additional information, please contact Rachel McCarter (Project Manager) of New England Civil Engineering at 978-973-6531.